Harris Pye

Harris Pye’s team of Marine Design Engineers and other highly qualified personnel have extensive experience in various installation and retrofit projects within the marine sector; numerous Exhaust Gas Scrubber Systems, Low Sulphur Diesel Oil Conversions and Ballast Water Treatment plants.

The Harris Pye Group offers over 40 years’ experience within the Marine industry. We offer complete turnkey installation packages; initial site surveys, feasibility studies, 3D laser scanning and modelling; ultimately progressing to detailed engineering and design, resulting in a cost effective installation program tailored to client requirements.

We pride ourselves on our ability to mobilize on short notice. Our services are available during dry dock, quayside, or in service; on a 24/7 basis. Harris Pye’s efficient and effective project management throughout the planning, design and installation stages ensure that there is minimal disruption to the ship’s itinerary. Opting to undertake installation works in service can significantly reduce downtime for the vessel by utilizing project planning to comply with Clients’ target dates, rather than depending on a docking schedule.

With fully certified workshops in the United Kingdom, Middle East, Asia and Brazil; Harris Pye offers an efficient and economical alternative to onsite manufacture / production through considerable prefabrication prior to installation, thereby reducing installation duration, cost and vessel downtime. In addition, Harris Pye operates dedicated clean shops for prefabrication of non-ferrous and exotic materials, even fabricating for OEMs to meet project schedules.

Clients will also benefit from local and globally discounted supply chain costs and reduced installation times. Harris Pye’s workforce includes fully versed, certified and accredited skilled workers for PE, PP, PE lined pipe, GRE, GRVE, SMO and conventional steel piping, all managed by dedicated project management teams liaising and coordinating with the clients on a daily basis to ensure seamless and efficient installations.

Table 1: Example scrubber analysis and installation timeline; pending scrubber manufacturer availability.

Please note timelines can be fast tracked and reduced to ≈ 8 months at a premium.

Description Example Timeline Accountable Party
System Selection (or HP advice) Ship-Owner
Desktop Survey Week 1 Harris Pye
3D Scan & Full Ship Survey Week 4 Harris Pye
Modelling Week 8 Harris Pye
Basic Design Approval Week 10 Ship owner & EGCS OEM
Detailed Design Engineering Week 18 Harris Pye
Procurement Week 14 – 26 Harris Pye
Pre-Fabrication Week 18 – 22 Harris Pye
Installation Week 22 – 48 Harris Pye / Shipyard
Commissioning & IOPPC Renewal Week 48 – 52 Class, EGCS OEM & Harris Pye
Live EGCS Week 52 Ship-Owner

Contact

Harris Pye DMCC
PO Box 127969, 12th Floor Mazaya BB-1
Mazaya Business Avenue
Jumeirah Lakes Towers
Dubai, United Arab Emirates

E: hpoffshore@harrispye.com
T: +9714 324 1535

W: http://www.harrispye.com